Wednesday, January 10, 2018

01/10/2018 - Horizontal drilling progress and completion of the pipe fusing

Project Update:



Horizontal Drilling Nearing Completion and Pipe Fusing Completed

Cardiff-by-the-Sea, CA, January 10, 2018



Construction work continues on the Land Outfall Replacement Project by the San Elijo Joint Powers Authority and general contractor, J.R. Filanc. Project information can be found at www.sejpa.blogspot.com.

Recent progress:

  • Inclement weather produced minor schedule delays as the crew shifted focus to storm water best management practices (BMPs) to protect the environment and worksite.
  • The third and final reaming pass (48-inch) commenced January 4th and approximately 700 feet of the alignment is complete.
  • Ongoing reaming and borehole preparation will likely continue through January 20th.
  • The installation of the pipeline is anticipated to commence the fourth week in January and will take approximately 48 continuous hours to complete.
  • The new high-density polyethylene (HDPE) land outfall pipeline is 2,500 feet long and 30 inches in diameter.
  • The pipeline was delivered in 50 foot long sections and required onsite assembly prior to installation using a heat welding process known as “fusing” (see photo).
  • Currently, the land outfall pipeline is completely assembled and staged for installation at the San Elijo Water Reclamation Facility.
  • The contractor is now preparing to perform final quality assurance checks on the HDPE pipeline prior to installation.
  • Work to tie-in the new 30-inch line to the Escondido regulator structure in Manchester Avenue is anticipated to begin today, January 10th.


After the borehole has been reamed to the desired diameter (48-inch), the land outfall pipeline will be pulled underground through the borehole from the water reclamation facility to the beach. Once installed, the contractor will connect the new land outfall to the existing ocean outfall system. Work will continue 24 hours a day, 6 days a week until the installation is complete.  Ongoing work in Manchester Avenue is expected through February 2018 and will temporarily impact access to the San Elijo Nature Center.  Every effort will be made to reduce any inconvenience to the community.




The San Elijo Joint Powers Authority is a local wastewater and recycled water agency serving the communities of Cardiff, Olivenhain, Solana Beach, Del Mar, and Rancho Santa Fe. This project will safeguard public health, protect the local environment, and preserve public recreation opportunities along the beaches of Encinitas, Cardiff, and Solana Beach. Thank you for your patience while we work to protect our community and coastline.

Contact: 
Mike Konicke
760.753.6203 x77
konickem@sejpa.org

No comments:

Post a Comment